Yep already done that. Its how the Project manager assignment actually works that im stuck with?
Andrew,
Admin-> Admin Preferences-> Timesheet tab then select or tick 2 Approval levels - Project Manager and resource manager approval required and mark/ tick Project Manager must before before resource manager.