Shazia khan 👤 Member for 18 years 1 month
S
Shazia khan 👤 Member for 18 years 1 month

Thanks so much for you advise,



i did the same and its worked fine.



Thanks so much for Advise and Best regards

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi Shazia,

It is as simple as copy and paste then rename then start modifying as new Project. You can also export to XER and import to Methodology Management and use as a template or project fragment.

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Hi Shazia,



You can save it under a different name with the new project, and then modify it. That is easier.



With kind regards,



Samer