Reporting Multi-Resources in an Activity
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Vaughn,
Use Resource Assignment window for printing resources separately.
Note: All material resources will not sum up the qty together with Labor and non-labor resource. You cannot combine qty & hour but if there is equivalent cost for each, use cost and it will sum up all.
Primavera stores the resource quantity associated with an activity in the resource assigments table AND the activity table. Ouch. So whether you can see subtotals by resource depends which of those tables is the primary one in any report.
For example in the "Resource Assigments"screen you can see each resource as a separate row, but in the "Actvities" screen you can only see one row per activity.