Rola,
P6 has an option on Level Resources to Automatically level Resources when Scheduling. Just tick this option and your leveling parameters will be run when running (F9) Schedule.
Other options are clearly explained on the help button.
Hi Rola
There have been many debates in PP about resource levelling - it may help if you run a search on the subject.
I do not have P6 but Rodel or some other expert will answer your technical query.
My stance is that you should never allow the software to level the resources because you have no control over the outcome.
Best regards
Mike Testro