Calculation Error

C
Comert Vardar 👤 Member for 15 years 9 months

Problem is still unsolved. I will be glad if any help,recommends work for it.



Comert

C
Comert Vardar 👤 Member for 15 years 9 months

i just wanted to give an extra information about max units. so there is no related issue about max units, i know.



i checked budgeted units again.



real example from my schedule;

165 day long Bedding activity;

*Loader works:10h/d, price units:10,1$/h, budgeted units:1650 nothing wrong up to here,

but budgeted price; 166.500$

it must be 16.650$, as i know.



if that doesn’t make sense, i could send you print-screen shot from my assigned resources, my friend.



Thanks for help anyway.

R
Rodel Marasigan 👤 Member for 19 years 7 months

Cormert,

If your settings is $55/h x 100d x 10h/d = $55,000.00 and if the settings is $55/d x 100d = 5,500.00 therefore both of your calculation is wrong. Max unit 10h/d day doesn’t not control resource assigned. It is only the boundary that P6 will set that the resource assigned is over allocated if exceeded on the max unit defined. When assigning resources the default assignment is defined under Resource detail tab-> Default unit/time and not the max unit/time under unit & prices. Can you check your settings and the budgeted unit assigned to your resources which will be the multiplier from define price/unit?

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts