Hi Comert,
How about your calendar? Did you check it also?
Cheers,
Problem is still unsolved. I will be glad if any help,recommends work for it.
Comert
i just wanted to give an extra information about max units. so there is no related issue about max units, i know.
i checked budgeted units again.
real example from my schedule;
165 day long Bedding activity;
*Loader works:10h/d, price units:10,1$/h, budgeted units:1650 nothing wrong up to here,
but budgeted price; 166.500$
it must be 16.650$, as i know.
if that doesnt make sense, i could send you print-screen shot from my assigned resources, my friend.
Thanks for help anyway.
Cormert,
If your settings is $55/h x 100d x 10h/d = $55,000.00 and if the settings is $55/d x 100d = 5,500.00 therefore both of your calculation is wrong. Max unit 10h/d day doesnt not control resource assigned. It is only the boundary that P6 will set that the resource assigned is over allocated if exceeded on the max unit defined. When assigning resources the default assignment is defined under Resource detail tab-> Default unit/time and not the max unit/time under unit & prices. Can you check your settings and the budgeted unit assigned to your resources which will be the multiplier from define price/unit?