How to show nonwork time(neck) in collapsed bar

R
Rodel Marasigan 👤 Member for 19 years 7 months

Kinnar,

P6 don’t support necking on summary band. The work around is to create a WBS Summary Task and apply the necking then filter only WBS Summary Task as sample below:

Bar Necking Summary

K
Kinnar Patel 👤 Member for 20 years

Hi Rodel,

Thanks very much for reply.

It can show neck in the bar when its not collapsed.

I wanted to show it on the bar even when it collased.

Like, 1 WBS have 4 actvities. When you collapsed it, shows 4 diffrent bars in a same line. I want to show neck on those collapsed bars.

Thanks.

Kind Regards,

Kinnar

R
Rodel Marasigan 👤 Member for 19 years 7 months

Kinnar,



View-> Bars and under Bar Settings tab mark the Bar necking required and if mark Show Bar when collapse on Group Band settings as shown below.

Bar Necking

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts