Schedule %

R
Rashid Iqbal 👤 Member for 16 years 2 months

Vellu,



Unit and Duration percent will roll up automatically, schedule and physical wont. I will not suggest Duration % but go for Unit % if you can…. and if my memory serves me right there is some way around of rolling up the physical % as well.



Use only one to display...

V
vellu shanmugam 👤 Member for 16 years 6 months

yes i agree with you but my case is the schedule is not ahead. although at each individual activities the schedule % & actual % are indicating figures but when i group it & checked the grandtotal only the actual % showing 6% but schedule % still shows 0%.



Is there any setting to do with it?



example;



activity name; schedule %; actual %;





Procurement; 100%; 100%

Manufacture; 52%; 5%;

Delivery 0%; 0%



Grandtotal 0%; 6%




S
Shazia khan 👤 Member for 18 years 1 month



if you are ahead of baseline schedule then it may not roll out,



example baseline activity start date is 25-Sep-10



but you have start this activity on 25-Aug-10 means you will not able to see your sch.% progress, that will shows after 25-sep-10.



i am not sure about your problem may be this is the case,

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts