Hello Kaythrine,
I did notice you are presently in design related planning. There are lots of scenario here:
Probably 1: The provisional sum relates to construction of structure with no exiting design drawings, say for example bldg A, roads and parking, etc. Solution: you can have a WBS showing this structures at the same time allow for one line activity describing the structure. This is important because you have to capture the duration of its provisional sum relating to the construction of each structure to give a clear picture on what the construction duration might be.
GB, PTL, TY
Scarlett
Hi Bigueras
You do not to have to allot a space for provisional sum .In the project programming structure you can assign one WBS in specific for provisional sum and its related activities
Re: Scarllet, Huzzle, Tom, & Shahul thanks for the input!
I think I really need to make a space on my WBS for provisional Sums, as of now we are still disecting the ducuments and specs & stitching out WBS & BOQ.
Hi
Check this link ,you might get few informations
http://www.brewerconsulting.co.uk/cases/CJ9636CL.htm
Its worth remembering the difference between defined and undefined PSs:
Defined provisional sums are sums of money intended for elements of the Works which have not been sufficiently designed but where there is certain defined information available.
The required information is specified within General Rule 10.3 of SMM 7 which requires the following details to be provided in respect of every defined provisional sum in the Bills of Quantities:
(a) The nature and construction of the work.
(b) A statement of how and where the work is fixed to the building and what other is to be fixed thereto.
(c) A quantity or quantities which indicate the scope and extent of the work.
(d) Any specified limitations and the like identified in Section A35 of SMM 7 (limitations imposed by the Employer e.g. access, disposal of materials found, working hours).
If the information specified in General Rule 10.3 of SMM 7 is not available the Contract Bills should describe the provisional sum as ‘undefined’.
As noted above, General Rule 10.4 of SMM7 states that ‘where Provisional sums are given for defined work the Contractor will be deemed to have made due allowance in programming, planning and pricing preliminaries’.
In my experience a lot of Clients will claim a provsional sum is defined WHEN IT IS NOT.
So, to cap, you need to included all DEFINED PROVSIONAL SUMS ON YOUR PROGRAMMES !!
Hi Kathrine
I just looked up definition of PS on google and this is what it gave me:
A provisional sum is an estimate of the cost of carrying out particular work. The estimate includes the cost of supplying any materials needed for the work. An estimate is required if, after making all reasonable enquiries, the builder cannot give a definite amount for the item at the time the contract is entered into.
For example, when estimating for earthworks and excavation at the beginning of a job, the builder can work out a fairly good estimate of the amount of money required for the job without knowing what is actually under the ground. However, it is impossible to be absolutely certain about the final costs as it is based on rates. If the total volume in M3 of rock excavated was greater than the estimated amount, then the increase in cost is based on the rate stipulated in the contract.
Any difference between the provisional sum listed in the contract and the actual cost is paid by the client. This in effect changes the contract price.
Hello Kaythrine,
Welcome to Planning Planet, the best planet for planning engineers, planners and anyone interested to know about planning, scheduling, project control, contracts, etc.
Im also from Philippines and in my college days, I have not heard of provisional sum in the study of contract. During my practice in Philippines, I have not heard of provisional sum because most of the contracts are lump sum.
To answer your question:
Provisional sum are money allocated for certain activities that will be use at the discretion of the Engineer or client representative. Meaning while the Contractor quoted for an activity in the provisional sum, the Contractor needs the approval of the client representative to use the amount in the provisional sum.
for example: road diversion
In some lump sum contract the road diversion can be lump sum, meaning including in the lump sum contract, but
in some contract, road diversion can also be provisional sum. so to continue with the elucidation, in the lump sum contract, the road diversion will be done as shown in the contract plan, however, in provisional sum, the client representative can direct the Contractor to do road diversion here and there until all the sum will be expended.
Does all contract have it? as elaborated above, not all contract have provisional sum since it all depends on each countries practice. In Philippines, it is seldom used, however, in commonwealth countries, it is used most of the time.
or is it present in contract/specs or docs? This all depends upon the practice. Generally, in Philippines it is not present. Of course if you have Davies Langdon and Seah as the Quantity Surveyor consultant, there is a big chance of its present. But the prevalence in Philippines is not having provisional sum since most of our projects are lump sum.
I hope you are not confuse now. but if your contract says so then you have to include provisional sum in your schedule since that is construction activities. It will also guide your client representative when to issue an instruction to use the provisional sum.
GB, PTL, TY,
Scarlett
RE: Shahul, I already started building up its WBS & stitch in the activities. My question is, Should I place a sole "Provisional Sum" WBS for all Provisional Items like this .....
Provisional Sum
Temfacil
Sand Filling
or this...
Preliminaries
Time Prelims
Provisional Sum
Temfacil....
....
Paving Works
Compaction
Subgrade
Sanfilling- Provisional Sum...
RE: Scarllet, We are having a hard time coming up with its Master Programme & BOQ since the we are not physically present in the location ( we are in the Philippines & the project & everything is in US). There are missing items on the plans which we are not sure if it is really missing or just a missing page :) Google pages and its map really do help a lot here, hee hee
right now I manage to identify some provisional as stated in the specs & drawings :)
Hi Kaythrine
Welcome to Planning Planet
Regarding provisional sums everything depends on the definition in your Contract or the Method of Measurement.
As has been stated before there are usually two categories:
Defined PS where a programme task is required and
Undefined PS where no task is required.
The problem is that in most cost plans the Provisional sums are described as defined but are really undefined.
The question you must put to yourself is:
From the information attached to this PS can I realistically draw up a resourced task or set of tasks and place it in my network.
I yes then do so - if no then do not put in a task but put in a linked up milestone where it may fall in the network.
Best regards
Mike Testro