Remaining Units/time

S
Shah Syed Zaheer 👤 Member for 16 years 5 months

Ask , Shazia Khan,

Ramadaan Kareem,

Original Duration*Default Hrs=Budgeted units

But it is changing for other activities.

Piping OD=10 BU=320 AU=320 and Remaining Units/time=32

Concrete OD=15 BU=480 AU=480 and Remaining Units/time=32

Only few of the activities have completed not all and only one common resource with default units is 8 hrs/day

How is the BU and AU and Ru/t getting changed.

Thanks in advance.

S
Shazia khan 👤 Member for 18 years 1 month

Hi-Shahab,



note that,



units/time * od= Budgeted Units.





cal. 6 days per week 8 hr per day,



please check your cal time prieod





8 hr /day 6* 8 =48 hr / week and 26 *8 = per months and 26*12 = / years make this correct setting and also check



your local holy day cal. and correct working time for per year.



check your Global which cal you are using this must be tick,



Budgeted units calculated based on activity

duration.



if you have 16 ,16 mean 1 resource assign to this activity and duration is 2 days, 2 * 8 = 16 same as 32 means 1 resource assign for this activity and original duration is 4 days 4 *8 = 32 units where as 8 is the unit/time and 4 is your activity original duration.



Hope it is work for you.


Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts