Insert each project into a new master project. Update the projects separately, report out of the master. If the four projects share common resources, remember to point the master project to the shared resource pool.
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Tue, 2010-08-10 19:49
You can use Insert Project and still can track project separately and update. This process will combine all projects and keep updated while tracking separately.
You can also use copy and paste method. This will combine projects but not track separately.
Member for
16 years 1 monthRE: How i can combine 2 or more projects y Microsoft Proj?
Hey Fellas...a lot of thanks for the help....
Thanks again
Member for
18 years 4 monthsRE: How i can combine 2 or more projects y Microsoft Proj?
Insert each project into a new master project. Update the projects separately, report out of the master. If the four projects share common resources, remember to point the master project to the shared resource pool.
Member for
19 yearsRE: How i can combine 2 or more projects y Microsoft Proj?
Jhorban,
You can use Insert Project and still can track project separately and update. This process will combine all projects and keep updated while tracking separately.