Total Float and Critical Activities

J
jeoffrey reyes 👤 Member for 17 years 11 months

Hi Moutaz,



I saw already your schedule. It seems that you have too much float which is not advisable. But to answer your query why you have a Float of 2days in your START WORKING activity?, you have to adjust your lag to its Successor;



A5310 Hand Over FS 105



then your float will be Zero. Also, put FF relationship if you are linking to Milestones not FS. As what I have mentioned in my previous post, you have to link a more logical relationship to achieve a good critical path. Try to avoid to much Float its no longer realistic....200days and more...you know what i mean.





cheers,





JEFF

M
moutaz aldeib 👤 Member for 22 years 5 months

Rodel, the longest activity does not create the critical path and I reduced the duration of that activity but nothing happened.



Rodel, Can I send you through your personal e-mail if you do not mind?



Regards,



Moutaz

R
Rodel Marasigan 👤 Member for 19 years 7 months

Moustaz,

It means that your longest activity create the critical path. If you reduce duration of that activity for exercise analysis you will see the effect why?

M
moutaz aldeib 👤 Member for 22 years 5 months

Thanks all for your response,



Rodel, the critical bar is defined and I filtered the critical actviities, I got only three activities which exist in the report and located in the longest path.



Regards,



Moutaz

R
Rodel Marasigan 👤 Member for 19 years 7 months

Moutaz,

Try to filter critical activities and see if all activities with 0 float will show. I suspect that critical bar is not define or tick that is why it is not showing red bars.

S
Stephen Devaux 👤 Member for 21 years 2 months

Of course, for critical activities, what you should be quantifying is not their total float, but their drag. Just sayin’...



(The fact that Primavera doesn’t compute drag means you’d have to compute it by hand, which makes it a bit trickier and more time-consuming -- but no less important. Of course, you could just switch to Spider Project or MS Project to have the software compute drag...)



Fraternally in project management,



Steve the Bajan

S
Shah. HB 👤 Member for 17 years 6 months

Hi Moutaz



Check the value assigned [I.e TF=0] for total float to mark the activities as critical. I am not sure about p6 but in p3 one can assign total float value ,check that ,it might help you

M
Mike Testro 👤 Member for 20 years 6 months

Hi Moutaz



Set the float display to 2 decimal places.



Best regards



Mike Testro

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts