Data Date

R
Rodel Marasigan 👤 Member for 19 years 7 months

Moutaz,

It depends on how your activities are calculated. If resource loaded and cost loaded it’s calculated by resource cost weightings and if not then by duration as default. You can also set using resource curves instead of activity % complete. The response of P6 also varies on the duration type settings combined with Percent Complete type settings.

S
Shah. HB 👤 Member for 17 years 6 months

Hi Moutaz



As of i knew there is no difference in data date in P3 & P6



Please check the results once again, i mean your workouts