How to show Overall Percentage Complated ?

I
Irfan Khan 👤 Member for 16 years 11 months
D
Duy Pham 👤 Member for 17 years

HI,



Your schedule need to be cost loaded to be able to display % complete at summary band (by using performance % complete)



You can search lots of topics about this subject here on planning planet especially from Mr. Rodel Marasigan.



Br, Duy