Updating sequence via excel spreadsheet

R
Rodel Marasigan 👤 Member for 19 years 7 months

Izam,

Yes you can use export/import spreadsheet function in P6 to update progress. Task is for updating activities and Resource assignment is for updating resource loading and actual. You must update one at a time and not both otherwise it will produce an unexpected result.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts