Problem in P5 when i change "Data Date"

R
Rodel Marasigan 👤 Member for 19 years 7 months

Vasilis,

I believed you are looking on the wrong date column. If you used Early Start and Early Finish date then all this date will move when activity is progress. Early start will be changed equal to remaining early start date. Use Start and Finish date which reflects the current date. Actual date is represented by Actual and Finish date columns.

F
Francis Moyalan, PMP,PMI-SP 👤 Member for 21 years 4 months

Hi Gents,



The ideal solution is to insert ’start’ and ’finish’ columns rather than early start or finish dates which will yield only the planned dates as ver 5.0 has got totally different definitions.



Hope this will respolve the problem.



Cheers

S
Shah. HB 👤 Member for 17 years 6 months

Hi



Check the column title since P5 has many dates which can be represented in the activity column section



If the gantt chart dates are correct then check start and finish dates column which should match

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts