Total float of the first activity

J
jeoffrey reyes 👤 Member for 17 years 11 months

Hi Moutaz,



I saw already your schedule. It seems that you have too much float which is not advisable. But to answer your query why you have a Float of 2days in your START WORKING activity?, you have to adjust your lag to its Successor;



A5310 Hand Over FS 105



then your float will be Zero. Also, put FF relationship if you are linking to Milestones not FS. As what I have mentioned in my previous post, you have to link a more logical relationship to achieve a good critical path. Try to avoid to much Float its no longer realistic....200days and more...you know what i mean.





cheers,





JEFF

M
moutaz aldeib 👤 Member for 22 years 5 months

Dear all,



There is no must finish by constraint and no constraints at all.



Regards,



Moutaz

S
Shazia khan 👤 Member for 18 years 1 month

Please check,



press f9 Schedule--Option--Define Critical as ---tick the total float less then or equal to 0h



may be this can be work for you.

R
Rodel Marasigan 👤 Member for 19 years 7 months

Moutaz,

It seems that you have a Must Finish by date define which might be the cause of the problem.

M
Mike Testro 👤 Member for 20 years 6 months

Hi Moutaz



Have another look at thread nr 3



Best regards



Mike Testro

M
moutaz aldeib 👤 Member for 22 years 5 months

Thanks everybody for response,



Rodel, only one activity out of three is long



I am really stuck with this program, I could not find where is the problem?



Regards,



Moutaz

J
jeoffrey reyes 👤 Member for 17 years 11 months

Hi Moutaz,



Though you have completed your program, you have to check your critical activities then once more link it to be more realistic with your logic.





cheers,

JEFF

R
Rodel Marasigan 👤 Member for 19 years 7 months

Moutaz,

Check the logic and filter the longest path. I suspect that it was lying on 3 long activities.

M
moutaz aldeib 👤 Member for 22 years 5 months

No multiple calendars, no resource in the schedule and no constraints.



Regards,



Moutaz

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Hi Moutaz,



Do you use multiple calendars in your schedule?



If you did not use any constraints of Start No Earlier Than type then it may be caused by multiple calendars (and this may be true) or resource leveling (and this is wrong - Primavera does not calculate resource constrained floats properly).

M
Mike Testro 👤 Member for 20 years 6 months

Hi Moutaz



Following Vladimir’s question here are a few more.



1. Do you use very long tasks - 30 days plus?

2. Are you using SS FF Links?

3. Are you using + - Lead Lags?

4. Are any tasks set ALAP?



Best regards



Mike Testro

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts