Fragnets

S
SAM SHAI 👤 Member for 15 years 10 months
F
Francis Moyalan, PMP,PMI-SP 👤 Member for 21 years 4 months

Hi,



I believe absence of fragnets are the most imp: disadvantage in Ver 6.0 when compared to Ver 3.10 as this helps a lot in relicating the same sequence while developing a detailed baseline schedule.



Methodlogy Management fragnets coild not be integrated or used in the Project Managment module.



Any comments?

O
Oliver Melling 👤 Member for 19 years 1 month

Sam,



In P6, Methodology Manager is supposed to be used to create standard fragnets.



We use it for things such as project mobilisation etc.



Regards

M
Mike Testro 👤 Member for 20 years 6 months

Hi Sam



Why don’t you start on it and then distribute it free of charge to all PP members.



Best regards



Mike Testro.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts