Why P3 Calculate backwards?

A
Angel Cruz 👤 Member for 16 years

Yup your correct, there is Float Constraint-Zero Free Float..ALAP



Tnx.

R
Rodel Marasigan 👤 Member for 19 years 7 months

Angel,

Can you check if it has Float constrain. Zero free float have that attitude same as As Late as Possible.

V
vex zex 👤 Member for 15 years 11 months

hi shahul,



just set the start date at project overview,

Then schedule..level...

U can get what u want

A
Angel Cruz 👤 Member for 16 years

Hi Shahul,



But the activity having no succesor, predecessor and constraint.



Could you please direct me to the similar topic you’ve said. I search the forum but didn’t find it.





Tnx in Advance.

S
Shah. HB 👤 Member for 17 years 6 months

Hi Cruz



It is due to the constraints which shows finish date earlier than start date



I have experianced the same and even the similar topic have been discussed in this forum.You could refer for your reference

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Activity may be of ALAP (As Late As Possible) type.

And the schedule may be calculated backward - check scheuling settings.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts