Shazia,
Thats all material cost. Samples of Expenses are Travels, Car rentals, Office Supplies, Consultants, etc.. and other one time cost that belongs to the Projects.
Dear Sir
Could you please advise me .
Material cost like Hvac. elevator, concrete , exterior & enterior .
where i can set in Material cost or i ca consider as expanses.
my resource is cost calculate from unit/time bases.
i have rate for resource per/hr.
Please advise
Shazia,
No but it will show a big float if in the middle of the program.
Sir
If i will if it is open then any effect on resource loading.
Thanks
Shazia,
At least have predecessors if last activity and should have both if in the middle of the program unless for special purpose.