Sir Mr.Rodel

S
Shazia khan 👤 Member for 18 years 1 month
R
Rodel Marasigan 👤 Member for 19 years 7 months

Shazia,

Total duration is based on Global Default Calendar. You need to change the Global Default Calendar and use 6 days calendar that you used and also under that calendar settings change the Time Period to match the calendar. (i.e. 10/d, 60/w...etc...)



For relationship lag decimals you have to change it manually. Make sure it match the calendar that activity use (i.e. for activity using 5 days 8h/d and activity using 6 days 10h/d)



Best Regards,

Rodel

S
Shazia khan 👤 Member for 18 years 1 month

Dear Sir



Thanks for your reply.



the total Duration still 254.8 days.



Could you please provide Steps by steps how to solve this problem.



how to fix relation lag decimal.



I can make it round figger



2. i have finished Milestone , i want close all activity ends , other then start and end activity,



this mile stone still leave with out Succ, because these are Finished MS



Best Regards

R
Rodel Marasigan 👤 Member for 19 years 7 months

Shazia,

Good Work! As I noticed on your schedule, the source of the problem is from changing calendar from 10hrs to 8 hrs which resulted to decimal places (i.e. 1d = 1.25d). Even you corrected the durations but relationship lag still have decimals that need to be correct. That should fix the problem.



Best Regards,

Rodel

S
Shazia khan 👤 Member for 18 years 1 month

Dear Mr.Rodel



I wish to inform you that i have fix the problem



I had change duration as well as relationsip.



now all activity has right start and finished time.





Best Regards

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts