Thanks for the quick response - tried it, but - deleted the summary bar in format bar styles the 300 odd individual bars are still there - I understand what you say regarding double clicking on each bar and clearing the format, but I really dont want to do it 300 time (double that as the procurement is indented withing the overall project bar as well so that I can use WBS )
Right click Gantt chart-> Bar Style then cut row or delete summary bar. You can also modify each bar by double click which bar to modify and clear all format for the bar that you dont want to show.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Rodel
I have found a way round this - Format - Layout and untick the always roll up gantt bars.
Andrew
Andrew,
Im not sure which summary bar it is so Im guessing. It maybe the group summary bars. Try to play on all summary bar and you may find which one.
Rodel
Thanks for the quick response - tried it, but - deleted the summary bar in format bar styles the 300 odd individual bars are still there - I understand what you say regarding double clicking on each bar and clearing the format, but I really dont want to do it 300 time (double that as the procurement is indented withing the overall project bar as well so that I can use WBS )
Cheers
Andrew
Andrew,
Right click Gantt chart-> Bar Style then cut row or delete summary bar. You can also modify each bar by double click which bar to modify and clear all format for the bar that you dont want to show.