Waste Water Treatment Plant Schedule

I
Izam Zakaria 👤 Member for 20 years 1 month

Rodel,



Thanks for your explanation buddy.Good enough for me to apprehend the process flow.

R
Rodel Marasigan 👤 Member for 19 years 8 months

Izam,

It depends on the design and locations of Waste Water Treatment Plant.



Critical activities varies on design, lead procurement items like mechanical equipments, aerators, pumps, cables, generators, clarifiers equipments, grit & screen, piping materials, structural, handrails, platforms, tanks, media filters,valves,Penstocks & Stop Boards, SCADA, PLC, Switchboars etc … and construction methodologies and commissioning, service proving, operator trainings and many others.



If designs consist of Waste Treatment plant, Recycle Treatment, Class A & Class B storage tank or lagoon then all of those have different criticality, especially on long lead items that mostly takes 3 to 6 months and if not available in the country then it will take more if coming from overseas.



Typical Items are:

A) Common Facilities:

1.     Earthmoving

     Bulk Earth works & Earth moving & backfill

     Landscape

2.     Civil Works

     Roads and pavements

     Roads Hardstand & Guardrails

     Permanent Fencings

3.     Mechanical Works

     Some mechanical equipments

     Underground piping

     Potable water piping

4.     Electrical & Communication Works

     Lighting Protections

     Area, Road Lightings & Flood lights

     Site lighting and small power

     Security Access & CCTV System

B) Waste Treatment Plant and buildings

1.     Inlet Structure

2.     Screening & Grit

3.     Balance Tank, Bioreactor & WAS pump

4.     Blower

5.     Clarifiers

6.     RAS Pump Station

7.     Dual Media Filter & Filtrate Storage

8.     Waste Buffer Tank & Pump Station

9.     Chorine Contact Tank

10.     Chemical Storage & Unloading

11.     Lime Storage & Unloading

12.     GPPS & Tanker Receival Pump Station

13.     Tanker Receival Facilities

14.     Electrical Building and Facilities

15.     Sludge Dewatering

16.     Odour Control Facilities

17.     Control Buildings

18.     Workshops

19.     Tanker Loading Area



If Recycle water treatment plant is also included then another major items like Ultra Filter, Switch room, UV disinfections etc…

It may include Storage tanks or lagoon and Pump Stations.



Hope this help.



Best Regards,

Rodel

Forum Sponsor

Top Posters

Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts