Delay issue confusion

T
tasnim yusoff 👤 Member for 15 years 11 months

Hi Mr Rodel,



I tried your method but i still have few questions regarding it.



My activies are related to each other. Ex :

First fix -> 30 days

second fix (SS 14 days after first fix) -> 30 days

Final fix (SS 14 days after second fix) -> 30 days





Does it mean original act equal to 59 days( duration from first fix to final fix) or i have to do each activities separately?



Original Act = LOE -> SS-> Split Original Act1 and FF-> Split Original Act2.



Does it mean i hv to link it to the new bar ( duration from first fix to final fix) or only to final fix activity?



Thank you








R
Rodel Marasigan 👤 Member for 19 years 7 months

Tasnim,

My usual approach is to split the activity that are affecting by client delay and insert a delay activity to push the remaining duration of split activity. The split should be actual start up to actual impacted (where activity cannot continue) and another part is the remaining duration of activity that cannot start until delay activity is finished. Then insert LOE activity link from actual start (SS) and remaining duration activity (FF) to represent the whole duration of split activity.



Example:

Original Act = 10 day

Affected by client delay start after 6 days for 5 days.

Split Original Act 1 = Actual Start to 6 days->FS->Delay Activity = 5days->FS-> Split Original Act2 = 4 days

Original Act = LOE -> SS-> Split Original Act1 and FF-> Split Original Act2.



Hope this help.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts