Arun,
My email is [email protected].
Send me the Email IDS
Regards
Arun
Dear Ronald,
You are correct, if we are talking about Total Float issue, then he might have something wrong with sequencing and linking of activities. I was referring to reducing the total time of the project.
With kind regards,
Samer
Samer,
What you mean is incresing the duraion by reducing resouces for the critical path.
regards,
Dear Arun,
Look at the critical activities and try to increase the resources to reduce the duration.
With kind regards,
Samer
Hi Arun,
Send me the pogram.
You can reduce float by
1. linking it properly.
2. Defining contractual milestone where you can link series of activities and acts as interim dates for computing total float.
3. resource it properly and leveling the resource.
regards,
Ronald