it is not possible that you cannot re-baseline a project: when you are re-baselining a project, you receive a message asking if you want to replace the existing baseline; click "Yes" to save a new baseline and replace the existing one
this is true for any MS Project release since the beginning.
Member for
22 years 9 monthsRE: Re-baselining a schedule in MSP
Hi there,
it is not possible that you cannot re-baseline a project: when you are re-baselining a project, you receive a message asking if you want to replace the existing baseline; click "Yes" to save a new baseline and replace the existing one
this is true for any MS Project release since the beginning.
Alexandre
Member for
17 years 9 monthsRE: Re-baselining a schedule in MSP
Hi Peace,
Could you be a bit more specific and provide us with a more detail?
What happens exactly when you try to re-basline? Do you get any error messages? How did you baseline the project in the first instance?
Regards,
Darren