once thanks for you valuable advise .
i have corrected , the cal timing and Activity moving to next day.
Thanks so much expert.
Shazia,
Yes change the time to 5:00PM or what ever the end of working period and that should correct the timing including other successors timing. Also make sure that all durations are whole number by showing the digits on duration format. (Edit-> User Preferences-> Time Unit tab and under duration format, change the decimal to 2 so you can see all durations with decimal and change it to whole number.
Mr.Rodel
Thanks you are right , it was the same what you advise,
should i change my cal timing now. or any.
Thanks
Shazia,
Check the time associated with your date. Material activity may finish 4:00PM instead of 5:00PM that is why Construction Activity starts on the same day.
(Edit-> Users Preferences-> Date tab. Under Time select 12:00 hour (1:30 PM) and tick show minutes)