Assume a floor in building construction projects where the last activity is tied to an activity named as floor completion(Dummy 1) and that floor completion is tied to respective sectional completion and finally sectional completion is tied to project handover
Please be noted that i might be wrong but i proposed to get the correct logic through discussion in this forum
To have better schedule, we should have better links or sequence(not depend on software itself) Of course every single activity shall have next activity. Otherwise U will have big gap in between early and late curves.
I wish I can help u but I dun know what kind of industry u involved. U have to know what is critical items on ur schedule and the best way is ask project team about the sequence. That is what I did thus far, but if the activity confirmed wont have succescor then link FF+++ with last completion activity.
Check your logic, you probably have too many activities without successors. Link them to a finish milestone that the project is aiming for, or it may have several finish milestones. Do a view log in P6 when you schedule and tidy up all the mess.
Id approach it by identifying which critical tasks have the most drag. Then Id compress the schedule by shortening them up, splitting them, or fast tracking them (SS relationships) wherever I could without damaging the project by increasing risk, etc.
Then if the critical path has changed, Id check which activities now have the most drag, and Id keep repeating this process until most of the float was gone and I had a shorter (and often more profitable!) schedule. If its shorter but not more profitable, Id see if a shorter project has value for the customer, and, if it does, negotiate an early delivery incentive.
Unfortunately, Primavera (unlike Spider or MSP with an add-on) doesnt compute drag, so youll have to do the drag calculation "manually".
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Shahul
It seems you are talking about Milestone stage completions.
These of course are perfectly valid as they have zero duration and assist in logic transfer on large programmes.
Best regards
Mike Testro
Hi Mike
Assume a floor in building construction projects where the last activity is tied to an activity named as floor completion(Dummy 1) and that floor completion is tied to respective sectional completion and finally sectional completion is tied to project handover
Please be noted that i might be wrong but i proposed to get the correct logic through discussion in this forum
.-Intermediate dummy activity
Arun,
To have better schedule, we should have better links or sequence(not depend on software itself) Of course every single activity shall have next activity. Otherwise U will have big gap in between early and late curves.
I wish I can help u but I dun know what kind of industry u involved. U have to know what is critical items on ur schedule and the best way is ask project team about the sequence. That is what I did thus far, but if the activity confirmed wont have succescor then link FF+++ with last completion activity.
Cheers
Hi shahul
Whats all this about "intermediate dummy activity"?
How does that fit into proper planning unless it is a "Time Risk Buffer".
Please let us know.
Best regards
Mike Testro
Hi Arun
In addition , check the successors links and tie them to immediate ones with logical sequence.
You can also define some intermediate dummy activity or event monitor to draw realistic pro-gramme which reduces the total float.
Check your logic, you probably have too many activities without successors. Link them to a finish milestone that the project is aiming for, or it may have several finish milestones. Do a view log in P6 when you schedule and tidy up all the mess.
Its negative lag (- ve) lag
But this is not the right method
What is V lagging
Just use -ve lagging.
Hi, Arun.
Id approach it by identifying which critical tasks have the most drag. Then Id compress the schedule by shortening them up, splitting them, or fast tracking them (SS relationships) wherever I could without damaging the project by increasing risk, etc.
Then if the critical path has changed, Id check which activities now have the most drag, and Id keep repeating this process until most of the float was gone and I had a shorter (and often more profitable!) schedule. If its shorter but not more profitable, Id see if a shorter project has value for the customer, and, if it does, negotiate an early delivery incentive.
Unfortunately, Primavera (unlike Spider or MSP with an add-on) doesnt compute drag, so youll have to do the drag calculation "manually".
Good luck.
Fraternally in project management,
Steve the Bajan
Hi Arun
I replied that I do not have P6 software so I cannot help.
Best regards
Mike Testro
Thank you Mike
I have already send u the draft of the program for your comments .If u can give me ur personnel ID .I can send it to you
Regards
Arun V
Hi Arun
Tighten up the logic - do not leave any open ended bars.
If you are still getting excess float then your schedule is probably wrong.
Best regards
Mike Testro