Regarding Bar Color

V
Vladimir Liberzon 👤 Member for 25 years 4 months

In Spider Project there is also an option when bar color is selected by the software basing on user defined conditions (signals, street lights, ...).

Most simple example: if activity is late its bar is red, if it is ahead of schedule the bar is green, if it is on schedule the bar is blue.

This option can be switched on and off.

Sometimes it is useful.



Best Regards,

Vladimir

M
Mike Testro 👤 Member for 20 years 5 months

Hi Anbin



The general rule in respect of code colours applied to task bars is "less is better".



I use only four colours Green for level 4 tasks > Yellow for level 3 summaries > Cyan for level 2 and Dark Blue for level 1.



Avoid using multiple colours and patterns on tasks - it gives visual overload - the programme equivalent of a fireworks display.



Best regards



Mike Testro

R
Rodel Marasigan 👤 Member for 19 years 7 months

Anbin,

As far as my knowledge is concerned I haven’t read or encounter any ISO standard for Bar color on a Gantt chart.

By Default, Primavera use Green for outstanding activities, red for critical, blue for actual and yellow for baseline, MS Project use Blue for outstanding, red for critical and black for actual.

I know some company has define Standard Bar color for scheduling to avoid confusion and using same language when reading a schedule but for international or global none.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts