P3 - Multiple calendar used for manpower histogram
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
RODEL,
THANKS....i understand now....
Vex,
Y axis is define to max limit round up divisible by 5 major lines. If your max limit round up is not fit with divisible 5 then you will experience that kind of figure.
Ex: if total unit is 5000 / 5 = 1000 each major lines round up = 1000 = 100% but if total unit is 4500 /5 = 900 each major line round up = 1000 = 88.9% next 111%
thanks for the idea.i agreed with u.How about s-curve scales for the y-axis.Is ist can be done 100% or just mention 96.3% and the next 105%..how we defined this scales
Vex,
If you are using Task Dependent Activity type then activity calendar is used and only single calendar can assigned to activity but if you use Resources Dependent activity type then activity calendar is ignored and use resource calendar. This will allow you multiple calendars define on each resource like on my sample post #4.
On your problem you need to use Resource Dependent activity and create two calendars, one for day shift and one for night shift.
Ex: 08:00AM-05:00PM dayshift
05:00PM-12:00AM nightshift
For activity calendar you can assign 08:00AM – 12:00AM or 24 hrs calendar.
For your resource you need to create resources for dayshift and nightshift
Ex: Welder_DS, cal = 08:00AM-05:00PM – dayshift
Welder_NS, cal = 05:00PM-12:00AM – nightshift
Rigger_DS, cal = 08:00AM-05:00PM – dayshift
Rigger_NS, cal = 05:00PM-12:00AM – nightshift
And soon…
You have to define max unit/time per Resources per Shift then assign both on one activity. When creating a histogram use a shift calendar and shift Time interval as per my example.
Hope this will help.
thanks..
i have 4 trades ; rigger,welder,scaffolder,painter
all trades work day or night shift
how to combine all the trades if each activities must one calendar only and cannot be 2 calendars
as i know histogram run based on one calendar only and how p6 calculate the average manpowr histogram although we set the trades by multiple calendar..since the histogram run one calendar
vex,

P6 graphics is more advance compare to P3. If using Shift calendar you have to use shift timescale also in order to show the histogram. Max unit/time (Limit) should be define.
See sample below:
thanks for the advance...p6v7 still not used.
Just used p6v0 that not compatible for the histogram and s-curve graphically..like p3 graphic
As i know and do is one calendar for one projects..
Vex,
On new version of P6v7 Hours Per time period are now change to based on calendar assigned. If you select Calculate average per time period on Resource Profile Option, that should follow calendar settings.