resorce assignnment effective date

K
kumar s 👤 Member for 16 years 4 months
R
Rodel Marasigan 👤 Member for 19 years 7 months

kumar,

P6 recognise new max time/unit for new resource assigned as long as the activity date fall higher or equal to date specified on new max time/unit. You can show the column of max unit/time on resource tab to check at the same time.