Schedule % Complete in P6

D
Duy Pham 👤 Member for 17 years
Z
Zoltan Palffy 👤 Member for 16 years 11 months

SCHEDULE % COMPLETE indicates how much of the activity duration should currently be completed relative to the baseline schedule. This is based on where the data date falls between the activities baseline start and finish dates. 

R
Rodel Marasigan 👤 Member for 19 years 7 months

Duy Pham,



By Default P6 calculate Schedule % Complete by proportion of duration if no resources assigned. If resource is assign without rate or cost P6 will still use duration. If Cost loaded, proportion of cost towards duration if no resource curve assigned. If resource curves is assigned then P6 use curved proportion.