Dear Shahab,
Thank you very much for sharing it,
Gratitude!
Rick
Mike,
These days all are latest bridges without pits. Do you hav a pit for your weight bridge I dont think so.
Hellow Mike
Yes I was working on them thanks.
1. Crash Barrier 1 day
2. Cable routing 2 days
3. Ramp may require only 5 days.
Can give u detail tommorrow
Hi Shahab
You forgot the drainage.
It will also need a cabin for the operator and the calibration kit.
Best regards
Mike Testro
Hi I think these may help you.
Excavation 2 days
PCC 15 days
Ramp 10 days
Installation of mechanical eqpts 10 days
Electrical installations 7 days
All in all they shld finish within 40 -45 days
Hi Rick
Its just a box in the ground with some kit in it.
Whats your problem?
Best regards
Mike Testro