Many thanks for sharing your article Mr.Ronald
I co-published a paper titled, "Understanding P6 Dates" that explains Remaining Float. The secret is that Remaining Float is different from Total Flaot is you are using resource leveling. I hope that this helps!
Many Thanks Rodel
Shahul,
My understanding with remaining float is the same as total float and they computed the same. Once the activity is in progress the remaining early date = early date and when finished or completed remaining early date = null and early date = data date.