P6.1 distribution of budget or units over WBS

R
Rodel Marasigan 👤 Member for 19 years 7 months

Roozbeh,

You can create WBS Summary Task activity for every WBS that have budget against it. You don’t need to create link as it was automatically define the durations and start/finish date based on activities underneath within WBS band. Once created you can assign budget cost using resource or expenses. Resource is more flexible than expenses but both can produce budget spread and s-curve.

R
Roozbeh Taheri 👤 Member for 23 years 1 month

Rodel,



I haven’t done any budget asignment yet, and I do not have any wbs summary type activities in the schedule neither.

R
Rodel Marasigan 👤 Member for 19 years 7 months

Roozbeh,

In order to assist your query I need to clarify something. Is the budget assigned in WBS Summary task using resource or budget assigned using budget log in WBS Window?



If the budget is assigned on WBS Summary task then the answer is Yes but if the budget assigned using budget log in WBS Window then the answer is NO.



Note:

Budget log is for information only and normally used for initial planning / budgeting. The proper use if this field are for comparing initial budget to current budget of the Projects.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts