% Planned : % of works planned to be done (from baseline)
% Actual: % of actual work happened (you need to update)
You can insert both the columns and variance as Rodel already explained.
Regards
Balaji
Irfan,
Plan Progress is taken from your baseline. If you dont have baseline assigned by default P6 use current Project. Actual Progress is the % complete that you enter every cut-off date before running schedule (F9) on the new Data Date or status date. You can get the variance of the two by showing Column-> Durations-> Variance - Project Duration or Variance – Project Start Date or Variance – Project Finish Date.