Plan Progress vs Actual Progress

I
Irfan Khan 👤 Member for 16 years 11 months
B
Balaji Surendiran 👤 Member for 22 years

% Planned : % of works planned to be done (from baseline)

% Actual: % of actual work happened (you need to update)



You can insert both the columns and variance as Rodel already explained.



Regards

Balaji

R
Rodel Marasigan 👤 Member for 19 years 7 months

Irfan,

Plan Progress is taken from your baseline. If you don’t have baseline assigned by default P6 use current Project. Actual Progress is the % complete that you enter every cut-off date before running schedule (F9) on the new Data Date or status date. You can get the variance of the two by showing Column-> Durations-> Variance - Project Duration or Variance – Project Start Date or Variance – Project Finish Date.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts