Well Rola,
If the question is "How do I plan resources if I dont have a Production Rate and I am not familiar with this work (dont have previous experience)?" then as I already mentioned:
1> YES, I will definitely discuss/ask people who are familiar with that work and have had experience performing same. Not only the PROJECT MANAGER, I will even talk to skilled labor, foremen, supervisors, CMs, Design leads,,, whoever it takes!
2> Break down the work to components and see if you can estimate the components individually and work out an overall rate.
3> Research! RS means and other resources have compiled extensive estimation data that is continually updated. I saw long ago at JEA library something that applies to Jordan as well. Be careful though with this data as it might not apply completely to your particular case.
If for whatever reason you do not wish to ask / couldnt break it down and estimate / research failed! you still can cross check with BOQ/Budget rate for resources; if such information is at your disposal:
> Estimated price = Bare Cost + Tools Cost + MH Cost + OH + Profit
Use the MH cost and turn the money value into Man-hours; I doubt itll be helpful, but anyway, this is could be a good exercise to cross check any estimate you make to see if it is within the budget.
R,
Rami
Rami,
Thanks for your reply,ok but lets say there is no rates, and there is an impsed finish date. how will you determine manhours? what happens is that the project manager defines that there is 5 carpenters with 5 block layers etc.....
so you just load the numbers, is that the case for all project? I dont think that planning engineer plays its full role, he should be giving the PM the numbers not vice versa!!!
Hi Rola,
Well, from what I came to understand recently, Effort is the amount of resource expended on an activity, more precicely the man-hours. So calculation should be based on quantities and productivities to estimate Man-hours.
As for your second question; I have only once relied on a TEAM of QS to provide the breakdown I need per the schedule activities, but that was only because the project was:
1> A big project!
2> Invoicing was based on schedule progress. BOQ was copied in Primavera using Cost Accounts and Expenses. Progress was reported as Physical % Complete.
Generally you dont need detailed breakdown because:
1> It is timely and will probably need more time than that is required to submit the schedule.
2> You only need the best ESTIMATE of resource you can come up with.
What we normally do is:
1> Work out approximations from drawings and BoQ; in principal do our own QS using a combination of calculations, counting and proportionality; whichever applies.
2> Discuss with team members; each in his field, to give us their estimates (Samers point 8)
3> Previous Experience of similar Jobs; especially on-site experience or from site visits (Samers point 3)
4> Recently I used sort of Simulation which worked out pretty well; e.g., you need to work out the rate of fixing a wall mount CCTV camera; so you break down the steps needed to install it and then perhaps mentally do the job yourself as a skilled person and try to drive an overall productivity.The method also replies on 2 and 3 above and can be a combination of them.
5> QS would be my last resort and Id be glad if they helped giving their big load.
Hope this helps
Cheers,
Rami
Thank you everyone for your insights.
Samer, special thanks for the exhaustive list there: I have one thing to add:
21) Engineering, Engineering, Engineering!!! establish a reasonable engineering development and/or production (which ever the case applicable) and make sure that it is followed. Ive sen it over and again; projects being delayed due to Designs and Drawings not being planned properly. Allow for proper submittal/review turnarounds and expect at least two to three submittals per design/production stage. Monitor closely and notify frequently of required issue and reply dates.
whats-more, I agree with Stephen that Monitoring the Critical Path is perhaps the single most important activity a planner should perform. DRAG is appealing and I wish there was a tool that integrates right into P5/6!!!
Finally, I will attempt to match samers list to as follows Steps/Groups of Activities. My focus is updating and monitoring change not actual preparation. However, Samers points apply to almost every where:
1> Establish a Sound BL
(applicable samers:3,4,5,8,9,10,11,12,13,15,16,17,18,20)
2> Updating the Schedule
(applicable samirs pts: 1,2,3,4,5,6,7,8,9,10,14)
> Requesting and Collecting Data for the update
> Observing Contractual changes
> Challenge and Verify the data
> Status and update schedule
3> Compare to Baseline and Variance Analysis
(applicable samirs pts: 13,15,18,1,2,4,5,8,9)
> Observe any Slippage and Changes to Critical Path
> Compare to previous update Critical Path
> Establish Causation and Responsibility
> Quantify Change/Delay (delay analysis)
> Discuss/Report to Responsible party and investigate
ways to mitigate
4> Prepare Progress Report including findings from previous step which depending on the situation:
> Recommend (Discussed/Proposed) Corrective/Preventive
Action
> (OR) Internal Schedule Revision/Recovery
> (OR) Major Schedule Revision/Recovery
This is my basic understanding of what a planners daily dealings.
Thank you all once again.
Cheers
hi every body
I have some questions, how is effort calculated in time schedule, i have seen several ways and i want to know the better approch, and can somebody give me a comprehensive meaning of "effort"?
Another question, if i dont have a QS in my company, how will I be able to load resources into the activities?
in other meaning can you experinced plannners give us how do you work? I know the method mentioned in books but i think we need the things that you discovered because work in real life is not like the books.
I think this will be great idea!!!
Hi,
I think now that the 1st thing we do is
"Divide the Job into smaller Parts"
"Set Priorities for completion"
Maybe these issues come before constructability depending on factors related to customer and company capabilities.
With kind regards,
Samer
I agree with this:
"13. Critical Path. Watch it like a hawk in EVERY progress report. Make sure that you understand how it is behaving and why. Near Critical activities are also important. Hence, the float for each activity should be printed in each progress report. If your program is slipping, then you need to perform a trend analysis and understand why it is happening, then you need to work with the Construction Team on preparing a revised schedule"
But even more important is to include the Drag and Drag Cost of all current or future CP activities, as thats where youll look to revise your schedule.
Fraternally in project management,
Steve the Bajan
hi Rami
please in order to get a precise reply in this forum, perhaps it is better to explain your position !
are you the main contractor or a subcontractor ? the type of your contract, unit rate or lump sum ! the number of project control team, do you have QS ! do you have already a resource loaded baseline ! did your project management "care" about planning, did your Discipline superintendents are computer savvy or not ?
depending on that you can make your own strategy,
best regards
Mimoune
Dear Rami,
I have written this a year or so ago, but here it is again. The following is a list of the major task that a planner should continuously perform on a regular basis at site:
1. Daily Progress Reports. You will need to update the information about the progress of activities at site. A section will be used for manpower and a 3rd section is dedicated for material.
2. Weekly and Monthly Progress Reports. You will need to monitor the percentages completed (Actual vs Planned) in addition to any Issues the team has still unanswered.
3. Site Visits. Spend between 40-50% of your time on site. This is the only way you can monitor the activities and have a visual idea about what is ongoing at site.
4. Progress, Coordination, Special, Upper Management Meetings: You will need to keep your eyes focused on three items; Scope, Time, and Money. Any issue that changes the contractually agreed upon data you need client approval at the earliest.
5. Contract Documents. Read your Contract Documents; Specifications, drawings, and BOQs periodically in order to know exactly what is needed to be completed and what variations should be reported
6. Approved Program of Works. Review it as often as possible. The project site is dynamic and usually buzzing with activities. Tens, hundreds, and sometimes thousands of people are changing the shape of the project on a minute by minute basis. Reviewing the approved program of works will enable you to compare the planned versus actual as often as possible
7. Pictures. Take pictures while you are at site as often as possible. This is a great habit that will assist the planner in remembering the activities. Especially when you use the date and time function to appear on each picture taken.
8. Team members. Make sure that you know your team members on 1st name basis, in all disciplines. This is very much important when you need information from them. Communication is the most important activity for you to practice effectively.
9. Ask as many questions as you can. The more a planner ask the Construction team about their work and activities, the better the plan and schedule will be.
10. Long Lead items. Keep your eyes wide open on them. Without the material at site, work will not be completed.
11. Allow for uncertainties in the schedule. This will benefit you later on when the project progresses and you have delays.
12. Repeated activities. The duration to complete the same works is usually reduced with repetition since the construction teams would have learnt to do the same task faster.
13. Critical Path. Watch it like a hawk in EVERY progress report. Make sure that you understand how it is behaving and why. Near Critical activities are also important. Hence, the float for each activity should be printed in each progress report. If your program is slipping, then you need to perform a trend analysis and understand why it is happening, then you need to work with the Construction Team on preparing a revised schedule.
14. Changes at site. Make sure that your supervisors report every activity that they complete which is not shown on drawings or asked for in the BOQs. This is very important for cash flow on periodic period and later on in the preparation of Claims for time extension for the extra works completed on the Project.
15. Construction Methods. Always challenge your construction Managers to complete their works with better quality and faster ways of construction. (i.e, if you are working on a high rise, and you are late, you can ask to change the design of the last few floors from cast in situ to precast concrete). Hence you save the curing time, and at the same time having better quality
16) Production Rates: Use the information available to the project team at the start of the project, update it with the information of the actual supervisors working at site, and use the actual production rates that are reported in your daily reports. Contractors are very smart in increasing the productivity rates to achieve specific targets. Clear Incentive Plans to all team members can be used if necessary.
17) Complicated Jobs: start with a bottom-up approach for conventional construction. In case the details are not available, you can adopt a top-down approach by identifying the high level activities then proceed with more details.
18) Interconnected Activities: If you have two contractors or more working on the same building, things can get complicated. The only thing that will help you is to have them sit together and explain their intended method of construction. Open communication will solve a lot of problems and unveil several gaps not shown on initial schedule.
19) One, Two, Three, Four weeks look ahead: use them wisely to have less paperwork in your hand. But you need to remember the remaining activities as well. Give the construction team the information they need with the correct level of detail.
20) Milestones: This is a great way to complete your project. Having a milestone supported by a sponsor’s arrival (cutting the ribbon) will increase your productivity rates.
It’s a long list of things to do, but this is actually what is need to be done in order to control and monitor the Program of Works during the duration of the project.
If you can think of more things, please let me know, I am interested in knowing them.
With kind regards,
Samer
Hi Rami
I have found that the simplest and quickest way to collect progress data is to create an excell sheet with all the programme tasks in one column and a progress percentage in the next.
The site/section manager fills in his section every week and sends it back.
The percentages are Copy - pasted into the programme progress column and the drop line created.
If the manager "forgets" to send the progress % then all his section is reported as being late on progress and he gets a rocket.
What is the next step?
Work with the progress updates to keep the projct on track and report delays.
Best regards
Mike Testro.
Hello Shareef,
Thank you for your enthusiasm; I have to agree with you that obtaining actual progress data can be cumbersome and frustrating at times but eventually achievable; it would probably require multiple approaches:
1) Self observed/calculated data from periodic visits to the job site
2) Utilizing daily site Agenda/Diary/Report and trying to obtain the on-site personnel buy-in into your work to provide you with information you need
2) collaborating and working with office team memebers; QS/Cost Control/Document Control/Engineering etc,,, to complete the picture
Now, that being done and the schedule being updated on that basis, what is the next step.
Cheers,
Rami
Well said !!! Rami
The situation you have mentioned is very true. After a lot of struggle I have paved my own way to execute planning.
Preparation of the project programme of works is a difficult task but the updation of the programme is even more difficult.
Now like what you have said, well established companies would have their own way of data collection and updataion. Where as in relatively unorganised or small companies they hire planners just to meet the contractual requirement of having a planner at site. It is here where data collection becomes difficult.
* What I have decided is to make regular rounds to the site on daily basis and collect information such as Actual Start date & Finish date of activities, Resource Utilizations, suspension of work. Progress measurements of activities on quantity basis (which might not always be possible when there are works on different areas of the project and to wait till the working time is coomplete to measure qunatity might not seem feasible,so in this case I would resort to remaining duration of the work; and yes remaining duration not linked to percentage complete(which should be updated manually). Programme should be updated weekly.
The Actual resource utilization for each activity thus can be obtained and used in the programme rather than relying on the auto calculated actuals from programmes.
Now in the above procedures there are a lot of works which are actually rework such as resource utilization which is normally recorded by the time keeper and quantity measured by the QS. But in companies without proper procedures and inefficient work staff it becomes difficult to obtain the information we require and it would thus be better to do it on your own.
The next problem is cost updation this would require a lot of effort in actual cost data collection and to divide it according to our activity levels.
I would suggest to complete project controls on 2 or 3 projects using on Schedule and latr on start off costing.
Regards
Shareef
Hi,
I like the thread, thank you samer for starting it. I just feel and urge to grap this opportunity to get a question thats been floating on my mind for sometime now answered by you guys.
If you ask anyone what a planner is supposed to do: they probably wouldnt think twice before telling you: prepare a BL, resource load, cost load, engineering and procurement lists, monitor, update, and prepare reports,,, right! few will tell you about delay analysis and fewer will get into risk.
All of the above seem to be things related to and driven by the contract/client/consultant requirements and few companies appear to have reuqirements/process/procedure of their own in place to aid keep projects on track. the result is a planner/scheduler swamped by client/consultant fancy paper work and reports which bare little or no vlaue to the project.
I just want to know; away from general statements, what are the day to day planner must do, what kind of information/data/analysis/calculations/filters he can extract and provide for his team to help them make the project work.
In short, maybe a little Planning Guide of (1) what? and (2) how to! from your experince guys.
My question is soleley in the spirit of being abale to make a difference and be EFFECTIVE team members as schedulers and planners rather than just being the Wizard of Primavera and the wicked illustartor.
Thank you.
Cheers,
Rami
You are welcome Samer
By the way ,it might be help to other beginners too
Hi,
You might find this interesting to read.
http://www.projectsmart.co.uk/docs/100-rules-for-nasa-project-managers…
With kind regards,
Samer
Dear Shahul,
Very nice, thank you for sharing.
This is the first time that I read about the history of the word "milestone". Here is a google check on wiki:
"Roman Empire
Roman milestone on the former A66 between Kirkby Thore and Temple Sowerby (no inscription)Milestones were originally stone obelisks – made from granite, marble, or whatever local stone was available – and later concrete posts. They were widely used by Roman Empire road builders and were an important part of any Roman road network: the distance travelled per day was only a few miles in some cases.[citation needed] Many Roman milestones only record the name of the reigning emperor without giving any placenames or distances.[1] The first Roman milestones appeared on the Appian way. At the centre of Rome, the "Golden Milestone" was erected to mark the presumed centre of the empire: this milestone has since been lost. The Golden Milestone inspired the Zero Milestone in Washington, D.C., intended as the point from which all road distances in the United States should be reckoned.
"
With kind regards,
Samer
Hi to all
I have pasted the link which is related to basics of scheduling, it helped me to learn and brush up the concepts too
http://pmchallenge.gsfc.nasa.gov/Docs/2004-Pres/Sparrow.pdf
Hi,
I did a quick google search and found this small slide presentation. It is basic and classic
http://www.slideshare.net/DrKeelyKillpack/project-planning-basics-every…
Project Planning Basics - Everything you need to start managing a project
With kind regards,
Samer
Dear Rizwan,
I agree with you that the Drawings and the BOQs are the ingrediants (just like going to the supermaket with a shopping list to make a final dish).
Planning is another activity that you do to figure out the level of details that you are comfortable with in order to proceed with the executing of the work. You will need to divide the BOQ into more details to figure out how your are going to complete the deliverables. The drawings will identify the zoning and locations.
You start with the Drawings/BOQS---> identify another level of detail to complete the job --> identify the sequence that you will be completing the details to deliver the deliverables in the BOQ and follow the standard international standards to create a Schedule.
With kind regards,
Samer
Dear Planners,
According to my experience in construction projects, the most important thing is Drawings/BOQs, from where we can start our plan as we can estimate duration (from quantities) and resource(from man hours/machine hours)given in it.
Best Regards,
Rizwan Rauf
Hi to all
Thats correct and to be highly appreciated
Dear Shahul,
It is good also remember that it is also "fun" dat matters. Meaning that if you enjoy what you are doing then you will excel at it.
With kind regards,
Samer
Hi, Shahul.
There is one other question, actually, that should precede even the WHAT -- WHY? What is the value that the product, service or result of the project is designed to generate?
One of the problems Ive observed over the years is the lack of direction for the project team of what the value is that the project is intended to create. And without that info, the project team is limited in its ability to identify opportunities to increase that value (such as through the scope/cost/schedule trade-offs of the Triple Constraint Triangle).
Fraternally in project management,
Steve the Bajan
Hi to all
@ Samer, - it is really a good thread to share and assist juniors like me .Thanks for your kick start
@Stephen - Good message.In addition ,does it holds good ?
Scope-What is to be done ?
Plan-How to do?
Schedule-When to do?
Dear Rodel,
You are correct, the need to "speak up" and not to be shy from not knowing is important. So yes, it is essential for planners to "Ask about what they do not know".
This comes under the soft skills required to complete the job.
Thank you again for your remark.
With kind regards,
Samer
In addition to other post I would like to add communications and know to ask question.
Best Regards,
Rodel
Dear Stephan,
I really appreciate this note. I feel that this is important.
This is planning is a business plan perspective. Yes I agree the components of a business plan are essential building blocks to the success of business. In essence these seven steps are following the basic text recommendations to creating a schedule. 1, 2, and 3 are about scope, and details. 4, 5, and 6 are about the resources, and 7 about the sequencing.
Yes I agree following the unique way that has been identified to create a Schedule by the international standards is great for people with basic experience in Planning to create a Schedule.
Thank you again for your experienced input and proven ways to create a schedule.
With kind regards,
Samer
I always teach my students to start planning with the end of the project and to go through a process of WHAT, HOW, WHO, HOW MUCH, HOW LONG, and WHEN:
1. WHAT: What do you want to HAVE when the project work is complete, i.e. the product scope requirements?
2. WHAT: Of what components does that final product consist, and what are the requirements for those (in US DoD parlance, the CLINs, or Contract Line Item Numbers)?
3. HOW: What work activities have to be done to create each component, and then to put them all together, and to ensure quality?
4. WHO? What resources will be needed to do each of the work activities?
5. HOW MUCH? How much of each resource (including money) will be needed to get each work activity done?
6. HOW LONG? How long will each work activity take to complete?
7. WHEN? When can each activity occur in sequence, based on what must occur first, and when will the resources be available/unavailable for each activity?
Fraternally in project management,
Steve the Bajan
Dear Andrew,
This is actually a very good example. We have done this on one of the complicated projects. From the 3D we created a Model and then dismantled the model to understand how to build the structure.
Very good point. Thank you for bringing this up. It is not always that you can do this (creating a 3D model). In an oil and gas project, I had 50,000m2 of covered area with boxes that you need to assemble and create a structure that is shown only on drawings. Chances are you cant built the model on large scale projects.
The principle emphasised here again is "Constructability". That is ability to understand how it is going to be constructed.
With kind regards,
Samer
Samer,
Think outside the box for a minute, you say you wish to show junior team members some ways of thinking about planning; get them to think of examples of simple tasks from everyday life and have them simply break the task into smaller peices then ask them how they can measure the completion of those smaller activities.
Possibly even try to use an illustrated parts breakdown to show how things are built and that there would be a sequence to putting something together; the following is an example of an IPB.
www2.gol.com/users/neasham2/bronco/parts/pics/dana_30.gif
Dear Rola,
Yes you are correct, the BOQ is a good start but these are deliverables that are payable.
I agree that dividing the Schedule according to the CSI format is a great start. But the Schedule is also about how you are going to do the work. Constructability is not addressed by the BOQ.
Besides, you have to Plan First and Schedule Second.
With kind regards,
Samer
Dear Samer,
I think that the BOQ might be helpfull way to start with. one can divid the work according to bil numbers, then according to division. And this is helpfull when preparing the payment or cash flow.
Regards