Haresh,
Summary function is to summaries project information on Project Modules and Tracking modules. Once the Projects had been summarized, updated information will be published whether the projects are open or not. In Tracking module summary level are defines on Project Window-> Settings tab-> Summarized data-> Summarized to WBS level (i.e. 2) You already raised this queries of why Projects at Tracking Module are only expanding/collapsing to 2 branches. All information on this summaries are updated when summarized function has been run otherwise all closed project will show old information based on the last summarization.