Haresh,
The settings that controls the default unit/time of resource is under Resource-> Detail tab. Change Default Unit/Time of the resource use to 8.00/d.
Note: Planning unit setting control the unit/time. Under Users Preferences-> Time Units tab-> Unit Format. If hour is selected then Default unit/time = 8.00/d, if day is selected then 1.00/d