Oracle Primavera - PM6 Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Thu, 2010-06-10 06:39 Permalink RE: Start Milestone appears after succeeding activity Chris, If your activity id’s follow the sequence of logic then you can sort by start and activity id. Member for 18 years 6 months Member for 18 years 6 months Submitted by Oliver Melling on Thu, 2010-06-10 05:27 Permalink RE: Start Milestone appears after succeeding activity Sort by activity type also and this will put it how you want it. Log in or register to post comments
Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Thu, 2010-06-10 06:39 Permalink RE: Start Milestone appears after succeeding activity Chris, If your activity id’s follow the sequence of logic then you can sort by start and activity id.
Member for 18 years 6 months Member for 18 years 6 months Submitted by Oliver Melling on Thu, 2010-06-10 05:27 Permalink RE: Start Milestone appears after succeeding activity Sort by activity type also and this will put it how you want it.
Member for
19 yearsRE: Start Milestone appears after succeeding activity
Chris,
If your activity id’s follow the sequence of logic then you can sort by start and activity id.
Member for
18 years 6 monthsRE: Start Milestone appears after succeeding activity
Sort by activity type also and this will put it how you want it.