WBS for a Substation

P
Pacifico Pallasigui 👤 Member for 22 years 4 months

Shahul,



Thank you very much, but im preparing only the construction part of the substation like Civil, MEP and Finishing work without the procurement activities. I’ll just want to know the more or less the duration for Civil, MEP and Finishing for a 6,000 m2 substation.



Thank You

Pacifico

S
Shah. HB 👤 Member for 17 years 6 months

Hi Pacifico



Check the long lead material procurement duration with your project team because in substation you will find many equipment on approval of submittal they will undergo factory acceptance test which consumes some duration in some case it is critical

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Pacifico,



It depends on the location and the environmental factors. Say you need 3-6 months for procurement of equipment, and during that time you can get the Civil Structures up.



Say 9-12 months as as starter.



With kind regards,



Samer

P
Pacifico Pallasigui 👤 Member for 22 years 4 months

Planners,





I am preparing a schedule for an 2 nos. of electrical substation here in Saudi Arabia with area = 6000 m2 . Around how many months is the duration of this partion?



Thank You



Pacifico

S
Shaiju Thomas 👤 Member for 20 years 2 months

Hi Hady,



Installation works in the substation can be broken into following;



1. Installation



1.1. MEP works inside substation

1.2. Installation of substation equipments (transformers, MDSs etc)

1.3.Power Cable Installation

1.4.Bus duct installation

1.5.Control Cables installation

1.6.Cable terminations.



2. Testing activities



2.1.Transformers and Panels dry check

2.2.Cable testing

2.3.Transformers and Panels testing (protection tests)

2.4.System sequence tests

2.5.Cable HIPOT tests

2.6.Authority Inspection and witness tests

2.7.Final commissioning and Power On



Hope this will help

M
Mike Testro 👤 Member for 20 years 5 months

Hi Adi



Just make sure that you can get the kit into the building before you seal it up.



Best regards



Mike Testro

A
Anoon Iimos 👤 Member for 19 years 8 months

The construction of a concrete substation is like any other concrete building but you need lots of block-outs. If it is air-insulated, then you have air-conditioning system.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts