Re-scheduling and re-sequencing of activities

R
Rodel Marasigan 👤 Member for 19 years 8 months

Ronn,

The proper way and good practice of maintaining the schedule is reflecting the true sequence and correct methodology on site to make it a realistic schedule but make sure that baseline is preserve. The use of baseline is to compare the actual reflection on site vs target. Make sure all changes are documented and approved to make it easier to trace back the history. If the baseline is totally out of the blue from current schedule then make a suggestion or an effort to change the baseline and reflect the actual methodology and sequences maintaining the original baseline milestone date and contractual key deliverable date if possible. Make sure that new baseline is approved by the both parties (client and your management) before using the new baseline. If the critical path is change then make sure that the new critical path is agreed by both parties and not deviating contractual issues.

Forum Sponsor

Top Posters

James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts