M&E Services Commissioning Network

S
S Z 👤 Member for 14 years 5 months

Hi,

 

May i have a commissioning schedule (in P6 .xer version: 6) or most important commissioning activities for Civil, Electrical, Mechanical and Piping.

 

I will be glad if someone help me.

 

 

Thanks

[email protected]

M
Mike Testro 👤 Member for 20 years 5 months

Hi Andrew



One furthe point - if there are periods in the comissioning programme that relate to time - not work - such as a static presuure test over 24 hours - make sure you allocate a 24hr/7day calendar to the bar and set the duration in calendar hours/days.



Best regards



Mike Testro

K
Konstantinos Parsalidis 👤 Member for 20 years 3 months

Hi Andrew,



Yes, all links are FS; however, the "3rd dynamic flush" and the "dose passivator & bioside" can take place at the same tiem, i.e. there are FS to "add & circulate cleaner" and then lead to "backflush & forward flush main plant & equipment"



I hope this helps.

A
Andrew Owenson 👤 Member for 17 years 11 months

Mike



I know that, You are preaching to the converted. what I meant is - are all the activities listed in the detailed programme section on a finish start to each other, or are any of them carried out at the same time.



Regards



Andrew

M
Mike Testro 👤 Member for 20 years 5 months

Hi Andrew



All programmes should be FS logic.



Best regards



Mike Testro

A
Andrew Owenson 👤 Member for 17 years 11 months

Konstantinos



Thankyou for your input. Can I assume that the detailed programme are all finish start? Very useful thankyou again.



Andrew

K
Konstantinos Parsalidis 👤 Member for 20 years 3 months

For a typical mechanical system (usually LTHW or CHW), the requirements, water treatment and commissioning activities should be:



Requirements:



1) Power available to the system pumps (temporary or permanent)

2) Drainage system available (temporary or permanent)

3) Water supply available

4) Pipework completed, pressured tested & signed off



Water Treatment & Commissioning activities:



1) System Flush (static and dynamic) - approximately 20 days

2) System Chemical Cleaning - approximately 10 days

3) Fill & Vent System - approximately 2 days

4) System Proportional Balance - approximately 10 days

5) Regulate & Balance Equipment - approximately 5 days

6) System witness & sign off



For a bit more detailed programme:



1) Static Flush

2) 1st Dynamic Flush

3) Dose & circulate bioside

4) 2nd Dynamic Flush

5) Add & circulate cleaner

6) 3rd Dynamic Flush

7) Dose passivator & bioside

8) Backflush & forward flush main plant & equipment

9) Backflush & forward flush terminal units (eg.g FCUs, depending on the system)

10) Dose final inhibitor & bioside

11) Final tamples taken (7 days from the last activity; this is a milestone)

12) Laboratory analysis of final samples

13) System witness & sign off



Of course, this depends on the scope of works and the contract requirements. Also, I have found it useful to list all your systems; you can use the consultant’s schematics for that.

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Andrew,



You can visit www.usgbc.org and check the LEED documents;



"

LEED 2009 for New Construction and Major Renovations:



Commissioned Systems

Commissioning process activities must be completed for the following energy-related systems, at a minimum:

Heating, ventilating, air conditioning and refrigeration (HVAC&R) systems (mechanical and passive) and

associated controls

Lighting and daylighting controls

Domestic hot water systems

Renewable energy systems (e.g., wind, solar)

"



With kind regards,



Samer

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Andrew,



You might want to list the systems that you have. Sometimes up to 17 EM systems depending on the client.



You also need to know the standards and the specifications that you are working with. Some buildings have "Fundamental Commissioning" and others require "Enhanced Commissioing". These terms are associated with the new Green Buildings Requirements.



If you are working on certifying you building, then you might want to consider working with Energy Management Companies who have indepth experience about commissioning of buildings.



With kind regards,



Samer

M
Mike Testro 👤 Member for 20 years 5 months

Hi Andrew



For a normal construction programme the commissioning section need not be too detailed.



This is a typical list of tasks and milestones.



1. Plant run up and test - about 10 work days.

1.1 Lead in Milestone:

All services connected

All systems complete to 2nd fix

All plant installed and linked to risers.

All service risers closed and locked

2. Static tests for each level or fire break zone - about 5-10 days per level

2.1 Lead in milestones

Each level systems finals completed

Plant run up completed

3. Final Completion test & commission - allow at least 30 days

3.1 Lead in milestones

All static lests complete

All other trades - including snagging and clean and clear - complete - in other words no one else in the building.



The M&E specialists will of course have their own commissioning protocols and sequences but this level of detail is not needed provided you allow them enough time and exclusive access.



I hope that helps.



Best regards



Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts