Budget Units is linked to Duration
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Haresh,
The reason why your duration change when budget units is change because you use a duration type "Fixed Units" or "Fixed Unit/Time" and resource "Drive Activity Date" is tick. If you used this duration type settings and dont want to affect your duration when changing Budget Units then you have to un-tick "Drive Activity Date" under resource assignment on each resource. Alternatively use Fixed Duration and Unit" or "Fixed Duration and Unit/Time". Using this settings will ignore "Drive Activity Date" settings on resource which I already explain to your before when you are querying about P3.x Driving resource equivalent to P6.
Try to Use Duration type Fixed Duration and Units