Resource: One Supervisor for the full term of a Project

R
Rodel Marasigan 👤 Member for 19 years 7 months

Ruel,

Use Level Of Effort activity link SS to first activity where the foreman assigned and FF to last activity and assign resource foreman. If will automatically adjust if the last activity move forward or backward.