Dear Yaser,
Usually we recommend that the Construction team is involved in the planning of the activities that will be executed.
I recommend that you start with these major headlines;
1. Material Submittals.
2. Shop Drawings.
3. Procurement
4. Construction
5. Commissioning and Closeout.
You will need to read your BOQ in order to determine the material submittals that need to be submitted.
You need to read your Issued For Construction Drawings to determine the construction drawings that you want to include.
The Procurement of the long lead items; especially the Structural Steel and the Equipment needs to be listed and determined
The Construction Activities and sequencing can be listed and determined; start with
Substructure
Civil, Electrical, Mechanical
Super Structure
Civil, Electrical, Mechanical
Structural Steel
Finishing
Commissing as per Plan
Handing Over as per Contract Agreement
With kind regards,
Samer