Summary Schedule % Complete

R
Rodel Marasigan 👤 Member for 19 years 7 months

Behnaz,

All cost will be calculated. If no cost but have resource unit only then it will not included in calculation. (i.e. resource without rate)

B
Behnaz Soleimani 👤 Member for 16 years 1 month

thank you very much sir;

but when thsre is not any resource assign to activities, their schedule % Complete in summary calculated zero .

another question, when we have diffrent resource assign to activities,is it possible that it calculate Schedule % Compltet in summary base on specific one ( not all cudgeted cost, just for example for Labor unit cost)

thank you

Behnaz

R
Rodel Marasigan 👤 Member for 19 years 7 months

Behnaz,

By default if not resource cost loaded a proportion of duration up to the data date. If resource loaded with cost a proportion of cost up to the data date.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts