It follows your schedule options or preferences. If resources is over allocated then it will not level the resource.
Try some experiment then level the resource first to make sure that date are moving then run the schedule and add risk. If you are experimenting 2 or three activities then it will not work because all floats are already zero and critical so it will just give a new date if impacted unless 2 or three activities are not link but have same resource.
Note: Don’t forget to tick Level Resource During Scheduling
See Sample Schedule below before running P6 Risk module : WBS Requirement Settings have 17 float
Yes Rodel, I understand the risk will not impact the schedule........
But we have a schedule impact analysis , which has the following column i.e. WBS Total float , Project total float and Project Finish date.....atleast the impact of risks should be shown in this column.....if we calculate risks.....
If it does not shows the impact , then what is the purpose of having all this column...
Yes Rodel, I understand the risk will not impact the schedule........
But we have a schedule impact analysis , which has the following column i.e. WBS Total float , Project total float and Project Finish date.....atleast the impact of risks should be shown in this column.....if we calculate risks.....
If it does not shows the impact , then what is the purpose of having all this column...
Risk Impact calculates only exposure and it will not affect the schedule. Use Monte Carlo risk simulation or Pertmaster or any Risk simulation software that will calculate the correct risk impact based on different simulation and probability.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
haresh,


It follows your schedule options or preferences. If resources is over allocated then it will not level the resource.
Try some experiment then level the resource first to make sure that date are moving then run the schedule and add risk. If you are experimenting 2 or three activities then it will not work because all floats are already zero and critical so it will just give a new date if impacted unless 2 or three activities are not link but have same resource.
Note: Don’t forget to tick Level Resource During Scheduling
See Sample Schedule below before running P6 Risk module : WBS Requirement Settings have 17 float
Sample Risk Result below after applying Risk:
Yes Rodel, I understand the risk will not impact the schedule........
But we have a schedule impact analysis , which has the following column i.e. WBS Total float , Project total float and Project Finish date.....atleast the impact of risks should be shown in this column.....if we calculate risks.....
If it does not shows the impact , then what is the purpose of having all this column...
regards,
Haresh
Yes Rodel, I understand the risk will not impact the schedule........
But we have a schedule impact analysis , which has the following column i.e. WBS Total float , Project total float and Project Finish date.....atleast the impact of risks should be shown in this column.....if we calculate risks.....
If it does not shows the impact , then what is the purpose of having all this column...
regards,
Haresh
Haresh,
Risk Impact calculates only exposure and it will not affect the schedule. Use Monte Carlo risk simulation or Pertmaster or any Risk simulation software that will calculate the correct risk impact based on different simulation and probability.