Haresh,

It will show depends on the settings that you selected. If you look closely on the right panel window only open project will have equivalent value even all resources are shown on the left panel window. If wanted only resource for open project whether open project settings is selected or not right click left panel window and select Filter by-> Current Project’s Resources