Jeffrey,

It should be the same except if you define some of them are not using resources and used status tab-> labor units Or expenses tabs.

If using only resources units then the only reason why it has difference is on Resource Assignment Window maybe filtered. Check the filter and remove if any and you should have same remaining units for both activity usage spreadsheet and resource assignments.