Revised shedule -

M
Manoj VS 👤 Member for 16 years 3 months
S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Manoj,



If things didn’t change, then the Constraint should stay as is.



The basic concept is to keep the schedule current to the progress ongoing at site abiding by the Conditions of Contract.



With kind regards,



Samer

M
Manoj VS 👤 Member for 16 years 3 months

Thanks for reply Mr Samer Zawaydeh.



In the case of revised schedule with out change in recourse or sequence – for Inprogress activities do we need to keep start constraint in the revised schedule ?

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Manoj,



Your schedule should represent your actual plan. If your plan didn’t change and you are just late, then you input the late dates of completion.



On the other hand, if you are changing the executing of the job; increasing resources, or some other constraint is now available, then you will update your Program of Works to reflect the actual conditions.



If you can be more specific, we can provide you with a more specific answer.



With kind regards,



Samer

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts