Revised shedule -
Forum Sponsor
Top Posters
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
Dear Manoj,
If things didnt change, then the Constraint should stay as is.
The basic concept is to keep the schedule current to the progress ongoing at site abiding by the Conditions of Contract.
With kind regards,
Samer
Thanks for reply Mr Samer Zawaydeh.
In the case of revised schedule with out change in recourse or sequence – for Inprogress activities do we need to keep start constraint in the revised schedule ?
Dear Manoj,
Your schedule should represent your actual plan. If your plan didnt change and you are just late, then you input the late dates of completion.
On the other hand, if you are changing the executing of the job; increasing resources, or some other constraint is now available, then you will update your Program of Works to reflect the actual conditions.
If you can be more specific, we can provide you with a more specific answer.
With kind regards,
Samer